spacer

Expertise : Marine : Tory Island Department_of_communication_Marine_and_natural_resource_2000

TORY ISLAND HARBOUR PIER & BREAKWATER CONSTRUCTION

The works are located at Tory Island approximately 12KM from the coast of County Donegal. The Contract comprised the placing of pre-cast concrete caissons underwater and in the tidal zone to form the vertical faces of a pier extension. The caisson units were filled with reinforced concrete and the central core of the pier was filled with mass concrete. A reinforced concrete deck and battered wave wall were constructed to complete the pier.

A breakwater was constructed comprising of rock core material, a filter layer, secondary armour and primary armour. The primary armour units consisted of “CORE-LOC” concrete armour of 12 tonne size placed on the trunk and on both roundheads of the pier extension.

The pier extension is in the form of an “L-Shape” comprising of approximately 36M of berthing space to the pier extension, 40M of berthing face to the “L” shaped pier and 15M of return quay face with a protective breakwater at the exposed end.

The pre-cast concrete caisson units and “CORE-LOC” armour units were manufactured on the mainland and transported to the island by a tug and barge. The concrete was batched on site and the concrete materials as well as the filter layer and secondary armour for the breakwater were also transported from the mainland.

The principal quantities were as follows:

Pier

Precast Concrete Caissons   257 No.
C40/20 Reinforced Concrete   2,540m3
Mass Concrete   6,450m3
Reinforcement   90T

 

Breakwater

Rock Core   1550m3
Rock Filter Layer   980m2
Secondary Rock armour   2,300m3
12 tonne Core-loc Armour Units   440 No

CLIENT
Department Of Communications, Marine & Natural Resources

LOCATION
Tory Island

VALUE
€3.7 million

PRINCIPAL ENGINEER
RPS (Belfast)

CONTRACT PERIOD
May 1999 – October 2000


sustainability
health and safety